CRITICAL: Professional Legal Escalation - COURT PROCEEDINGS THREATENED

Al Sarpong has instructed HCR Wright Hassall (formerly Wright Hassall LLP), a national law firm, to pursue his claims against KG Project Ltd. As of 9 January 2026, they have threatened to commence court proceedings if no response within 14 days.

3
Formal Letters
14 Days
CURRENT Deadline
Stuart Miles
Senior Associate
URGENT - Latest Letter (9 Jan 2026): WH states Benchmark's 10.12.25 response only addressed paragraph 20 (insurance). Demands full response within 14 days or will commence proceedings and seek costs.
Firm Details:
HCR Wright Hassall (trading name of HCR Legal LLP)
Olympus Avenue, Leamington Spa, Warwickshire CV34 6BF
Reference: 120683/1
Tel: +44 1926 883035
Email: Stuart.Miles@wrighthassall.co.uk

Summary of Wright Hassall's Claims

Al's Position (via WH):

  • KG Project accepted maintenance responsibility via SA Law letter (14 June 2023)
  • Current leak affecting Property from outside the demise
  • Estoppel argument - Al relied on KG Project's admission
  • Pre-action admission cannot be withdrawn
  • Threat of Tribunal proceedings under s.35(2)(a) Landlord and Tenant Act 1987
  • Demands for insurance policy disclosure under s.30A LTA 1985

Legal Threats:

  • Application to vary the Lease (s.35(2)(a) LTA 1987)
  • Application re: pre-action admission (CPR 14.1(2)(a))
  • Indemnity costs / Rule 13 costs in Tribunal
  • Summary offence for failing to provide insurance (21 days)
  • Alternative Dispute Resolution offered
Background: Al's Emails to Katerina (July 2025)
19 July 2025

Al Reports New Leak Issue

Al Sarpong → Katerina

Subject: 14 &16 CARROUN ROAD - PARTY WALL BUILDING PIPE / GUTTERING ISSUE FOR URGENT RESOLUTION

Al brings attention to issue with the shared wall at the back of the flats, particularly the pipe fixed in December 2024.

Following heavy rain, it appears the pipe or guttering is leaking onto the wall. Pictures attached.

Al's Request: "Please can I urge that this is addressed as quickly as possible with organising the return of contractors to fix this."

Notes he was advised by the contractor that fixed the pipe late last year that there could be an issue again in future - "a longer term and more resilient solution might be necessary."

View Original Email
23 July 2025 Follow-up

Al Chases Response - Leak Worsening

Al Sarpong → Katerina

Subject: Fw: 14 &16 CARROUN ROAD - PARTY WALL BUILDING PIPE / GUTTERING ISSUE FOR URGENT RESOLUTION

"I am still waiting on a response to my mail from last Saturday 19th July with regards to the leak that has sprung up along the party wall."

"We have had more bad weather this week and the problem has now exacerbated. The problem is concentrated largely in specific area, so it is unlikely to be a wider issue with the roof."

Critical Statement: "Once again, please can I request your assistance in getting this resolved as soon as possible, in the same manner as you immediately assisted Eleanor Henson when she raised the issue of the pipe last year."

Mentions Eleanor Henson (another resident/tenant) was assisted promptly with a pipe issue the previous year.

View Original Email
FIRST WRIGHT HASSALL LETTER (3 October 2025)
3 October 2025 Formal Legal Letter WH Reference: 120683/1

Wright Hassall First Letter to KG Project

Wright Hassall → KG Project Ltd (copy to SA Law)

Sent by: First class post, Recorded Delivery & email to katerina@kgplondon.com

Key Points:

1-3. Introduction:

  • Acting for Albert Sarpong, leasehold proprietor of Flat 14
  • Lease dated 8.11.13 between KG Project Limited, 14-16 Carroun Road (Management) Limited, and Charles Willis
  • Copy sent to SA Law out of courtesy - requests confirmation if KG Project still instructing them

4-8. The Leak:

  • KG Project failed to respond to Al's emails dated 19.7.25 and 23.7.25
  • Leak impacting Al's Property - emanating from outside the demise
  • Photographs enclosed showing leak entering from corner of ceiling where eastern wall meets ceiling
  • Water trickles down wall onto skirting board
  • Al is mitigating damage using towels and bucket during heavy rain

9-10. Lease Interpretation - THE KEY ARGUMENT:

  • Notes that 14-16 Carroun Road ("the Building") is NOT demised to Al - only specific aspects of the Property as defined in the Lease and Schedule 1
  • CITES SA LAW LETTER: "It is noted that your solicitor's letter to our client dated 14.6.23 accepts that it is your responsibility to keep in good repair and to maintain the Building. As such, it is your responsibility to investigate the leaks and deal with them to the extent that the Building is causing these issues."

11-12. Insurance Query:

  • Disappointing that Al has received no update in response to his emails
  • Requests confirmation whether KG Project has explored making an insurance claim pursuant to paragraph 2 of Schedule 6 of the Lease
  • Asks what the insurer has informed regarding the leak

13-14. Next Steps - 21 DAY DEADLINE:

  • Within 21 days, expects written confirmation of:
    • a. Proposals for addressing the leak
    • b. Information from the insurer as to whether the policy will cover the damage
  • Threat: "In the absence of a response within 21 days, our client will have to consider his options for further action"
  • Hopes to engage with KG Project about how to address the leak prior to winter weather
View Full Letter (PDF)

Enclosures with 3 October 2025 Letter

SECOND WRIGHT HASSALL LETTER (14 November 2025)
14 November 2025 Response to Benchmark Ref: RP2900 / 120683/1

Wright Hassall Reply to Benchmark Solicitors

Wright Hassall → Benchmark Solicitors LLP (Ross Paterson)

Sent by email only to: ross.paterson@benchmark-solicitors.co.uk

In response to: Benchmark letter dated 7.11.25

Implied Term (Points 2-3):

  • "As insinuated by your letter, the courts do have an ability to imply terms into a lease. It is not an unarguable point."
  • However, Al appreciates this is an "unnecessary preliminary issue" best avoided given context
  • Encourages Benchmark to seek clarifications on instructions before asserting this point

Variation of Lease (Points 4-5):

  • Section 35(2)(a) Landlord and Tenant Act 1987: Al is "at liberty" to apply to vary the Lease
  • Tribunal has jurisdiction to amend the Lease to deal with "the unsatisfactory provision of the absence of the covenant for your client to maintain the Building"
  • Al would rather avoid the expense and protracted nature of such proceedings - "only incur such costs as a last resort"

Estoppel Argument (Points 6-7):

  • Al "can make out a case" that he acted on a clear representation made by KG Project's instructed solicitor
  • Placed reliance on it by NOT taking matters into his own hands via a self-help remedy
  • Now suffering detriment of a leak that KG Project is "unconscionably refusing to deal with, having previously asserted that it was their responsibility"
  • KG Project is a corporate entity who can afford and appreciate legal advice - "Your letter is therefore too quick to dismiss an estoppel"

Pre-action Admission (Points 8-10):

  • Benchmark failed to explain WHY KG Project instructed SA Law to concede responsibility
  • "Courts would be slow to permit your client to reengage in relation to the concession made over the maintenance"
  • Notes Benchmark's letter "stops short of stating the previous advice received was wrong"
  • Appears to insinuate advice "could possibly be correct" - KG Project now asserts alternative position to "renege from its previous position"
  • Threat: Al will NOT consent to withdraw the previous position; reserves right to bring application under CPR 14.1(2)(a)
  • "The previous position was pragmatic, with the benefit of legal advice and the step back from this position would appear to be vexatious in nature"
  • Al would be "severely prejudiced if your client is allowed to renege on its previous admission"

Common Sense Arguments (Points 11-14):

  • KG Project owns the OTHER flat in the Building - reason enough to revert to SA Law's advice
  • If KG Project was a freeholder with no other interest in a 999-year lease, attempting to renege might be sympathised with - but this is not the case
  • Stance of not addressing the problem but also preventing Al from addressing it is "bemusing"
  • "Your letter offers no solution whatsoever"
  • Various lease obligations necessitate contact between the parties
  • Solicitors' duty to consider clients' interests - "not being served by putting up technical barriers to resolution"
  • If leak is left, it will impact value of BOTH properties

Previous Roof Works 2022 (Points 15-17):

  • Benchmark's assertion that Al's 2022 works "exacerbated the issue" is "baseless"
  • Renders KG Project's threat for loss "hollow" - no evidence provided
  • Fact that Al had no cause to report leaks until now "demonstrates that those works presented a short-term solution while your client refused to engage with its responsibilities"
  • If works would have caused issues, why no complaint in 2023 or 2024?
  • 2022 roof works were never presented as a long-term solution
  • Al made KG Project aware of issues in March 2021 - KG Project said it would consider and revert. No response received.
  • Al carried out short-term solution to address the issue
  • "KG Project has benefited from our client's diligence without making payment"
  • Hard to see how any alleged trespass could outweigh KG Project's failure to address the issue first
  • Photograph enclosed showing state of roof PRIOR to 2022 works

COUNTER-ARGUMENT: The March 2021 Notification Claim is MISLEADING

Wright Hassall asserts (Point 16): "Al made KG Project aware of issues in March 2021" to suggest landlord neglect. The actual emails tell a very different story:

Al's Email (31 March 2021):

"My only immediate concern would be the roof - there was a leak during a heavy bout of rain back in October. It has not happened since then... Is the roof solely my responsibility or does it come under the coverage of the freehold?"

Katerina's Response (1 April 2021):

"In regards of roof renovation issue I have to look into Lease Agreement and get back to you shortly."
WH's Implication The Truth
Ongoing roof emergency in March 2021 Leak was from October 2020 - 5 months earlier - and had already stopped
Al demanded urgent repairs Al asked an informational question about lease responsibility
Katerina ignored the issue Katerina acknowledged it and said she'd check the lease - reasonable given no emergency
2022 works were to fix the 2020 leak The March 2022 repairs were for a NEW, DIFFERENT leak - confirmed by Al's own email of 29 Jan 2023: "nearly a year since the leak first occurred"

View Full Email Analysis in Katerina-Al Timeline →

Insurance (Points 18-20):

  • Benchmark asserts leak is not an insured risk - "without your client's insurer assessing that is not your place to shut down this avenue"
  • Numerous storms this year - insurer may consider damage as storm damage (an Insured Risk under Lease)
  • Requests disclosure of insurance policy and schedule - Al entitled under paragraph 2.3 of Schedule 6 of the Lease
  • Encloses Al's Section 30A Landlord and Tenant Act 1985 request

Next Steps (Points 21-23):

  • Insurance Deadline: Severity of failing to respond within 21 days - risk of a SUMMARY OFFENCE
  • Expects response to full letter within 21 days - especially given extra time afforded to receive advice from second firm of solicitors
  • Sensible for KG Project to reconsider position on retracting previous acceptance
  • Costs Threat: Al will rely on this letter when costs arise and seek indemnity costs or costs under Rule 13 if Tribunal proceedings
  • Al will consider any proposals for Alternative Dispute Resolution
View Full Letter (PDF)
THIRD WRIGHT HASSALL LETTER (9 January 2026)
9 January 2026 Proceedings Threatened Ref: RP2900 / 120683/1

HCR Wright Hassall - Chaser Letter with Court Threat

HCR Wright Hassall → Benchmark Solicitors LLP (Ross Paterson)

Sent by email only to: ross.paterson@benchmark-solicitors.co.uk

In response to: Benchmark letter dated 10.12.25

NOTE: Wright Hassall now trading as "HCR Wright Hassall" (merged/rebranded with HCR Legal LLP)

Complaints About Benchmark's Response:

  • Benchmark's letter dated 10.12.25 "only appears to deal with paragraph 20" of WH's 14.11.25 letter
  • Asks: "When does your client propose to instruct you to respond to the rest of the content of the letter dated 14.11.25?"

Note: Paragraph 20 of the 14.11.25 letter was the Section 30A insurance request - Benchmark apparently only responded to this single point.

Insurance Cover Query:

  • "It appears that the insurance may have storm and escape of water cover, as suspected at paragraph 18 of our letter dated 14.11.25"
  • Asks KG Project to disclose evidence of whether this cover has been explored with the insurer

14-DAY DEADLINE & COURT THREAT:

"Please respond within 14 days"

"In the absence of a response, we will take our client's instructions on proceedings to breach the impasse"

"...and invite the Court to assess all the relevant correspondence when arriving at a decision on costs."

CRITICAL: This letter was sent on 9 January 2026 - just 7 days BEFORE Ross Paterson stated he should stop acting for Katerina (16 January 2026). The 14-day deadline would fall around 23 January 2026.
View Full Letter (PDF)

Enclosure: Section 30A Notice (14 November 2025)

Al Sarpong served a formal statutory notice under the Landlord and Tenant Act 1985:

Leaseholder Notice for Insurance Cover

Section 30A and paragraphs 2 & 3 of the Schedule to the Landlord and Tenant Act 1985

To: KG Project Limited

Property: Flat 14, 14-16 Carroun Road, London SW8 1JT

  1. I am the leaseholder of the above Property.
  2. I make a formal notice to receive a summary of insurance cover in accordance with Section 30A and paragraph 2 of the Schedule.
  3. I make a formal notice to receive a copy of the insurance policy cover in accordance with Section 30A and paragraph 3 of the Schedule.
  4. As the landlord of the Property you are required to comply with paragraph 5.
  5. You are required to supply me with a written summary of the current insurance policy cover or a copy of the insurance policy cover within a period of 21 days beginning with the day on which you receive this notice.

STATUTORY WARNING:

"A person who, without reasonable excuse, fails to perform a duty imposed on them by or by virtue of Section 30A and paragraphs 2/3 of the Schedule to the Landlord and Tenant Act 1985 commits a summary offence and is liable on conviction to pay a fine not exceeding level 4 on the standard scale."

"The local housing authority has the power to bring a prosecution."

Signed: Albert Sarpong

Date: 8th November 2025

View Section 30A Notice (PDF)

The SA Law Letter Wright Hassall Cites

Wright Hassall's entire case rests heavily on the following letter from Stan Harris (SA Law) dated 14 June 2023:

Key Passages Being Used Against KG Project:

"Whilst there is no express covenant in the lease either on behalf of the Management Company or the freeholder to maintain, repair and decorate those parts of the building which are defined as Retained Parts the freeholder accepts that the obligations to keep in good repair and to maintain those parts of the building defined as Retained parts are the freeholders responsibilities."
"However, for the purposes of this letter, my client accepts that the obligations to keep in good repair and to maintain those parts of the building that are defined as Retained Parts."

Why This is Problematic:

  • This was an OPEN LETTER - NOT marked "Without Prejudice"
  • Can be used in court/tribunal proceedings as evidence of admission
  • Wright Hassall now argues this creates an estoppel
  • They argue KG Project cannot withdraw this "pre-action admission"
  • The letter admits there's NO express covenant - then volunteers to accept responsibility anyway
View Stan Harris Letter (PDF)

Additional Enclosure: Roof Photograph (Pre-2022 Works)

Wright Hassall enclosed a photograph which Al instructs shows the state of the roof prior to completion of the 2022 roof works.

This is presented to counter Benchmark's assertion that Al's 2022 works exacerbated the issue.

View Roof Photograph (DOCX)

Critical Dates Summary - With Strategic Notes

Green annotations indicate where WH's claims are incorrect or can be strongly argued against.

Date Event WH's Position COUNTER-ARGUMENT
October 2020 Single roof leak during heavy rain Not mentioned by WH KEY: This leak RESOLVED ITSELF. Al's March 2021 email confirms: "It has not happened since then"
31 March 2021 Al emails Katerina mentioning past roof leak WH claims: "notified of roof issues" - implies emergency ignored MISLEADING: Al was asking an INFORMATIONAL QUESTION about a leak that had already stopped. He said renovations should wait until "next year". NOT an emergency demand.
1 April 2021 Katerina responds to Al WH claims: "no response was received" FALSE: Katerina DID respond: "I have to look into Lease Agreement and get back to you shortly" - reasonable for a non-emergency query.
February 2022 Al carried out roof works (Solution Roofing) - £3,500 WH says this was for ongoing issue from 2021 DIFFERENT LEAK: This was a NEW emergency - not the same as Oct 2020. Al's 29 Jan 2023 email confirms: "nearly a year since the leak first occurred" (i.e., 2022, not 2020).
2 March 2022 Al notifies Katerina of completed works - ARGUE: Works done WITHOUT prior consultation or approval. No competitive quotes obtained. Payment to individual (JS Whitbread) not to company.
14 June 2023 Stan Harris (SA Law) letter to Al WH uses this as "admission" of responsibility PROBLEMATIC: OPEN letter (not "Without Prejudice") - can be used as evidence. Contains express acceptance of maintenance responsibility. However, context matters - see counter-arguments on estoppel.
22 June 2023 Stan offers £500 settlement Al rejected as "derisory" GOOD FAITH: KG Project attempted settlement. Al rejected reasonable offers.
5 July 2023 Revised offer: £978.75 Al rejected GOOD FAITH: Increased offer including ground rent waiver. Al still rejected.
December 2024 Pipe fixed at back of property Contractor warned of potential future issues ACTION TAKEN: KG Project DID arrange repairs - contradicts neglect narrative.
19-23 July 2025 Al emails about new leak issue WH claims no response received MITIGATING: Katerina was abroad and did not have access to her email. This explains any delay - NOT neglect.
3 October 2025 Wright Hassall first letter 21-day deadline set KG Project instructed Benchmark Solicitors in response.
7 November 2025 Benchmark Solicitors responds - ENGAGED: KG Project engaged solicitors and responded within deadline.
8 November 2025 Al signs Section 30A insurance notice Statutory request - criminal penalty for non-compliance RESPOND: Insurance documents (2025-2026) are available - should be provided to comply.
14 November 2025 Wright Hassall second letter New 21-day deadline Contains estoppel/admission arguments - see counter-argument section above.
10 December 2025 Benchmark responds to WH WH claims only para 20 (insurance) addressed INCOMPLETE: Full response to all points was needed. Strategy disagreement emerged.
9 January 2026 Wright Hassall third letter 14-day deadline - Court proceedings threatened URGENT: Requires immediate comprehensive response addressing ALL points.
16 January 2026 Ross Paterson terminates retainer Change of solicitor required £2,142 paid. Strategy disagreement. No substantive response sent to WH.
30 January 2026 Extended deadline (Ross requested extension) WH may commence proceedings after this date EXTENDED: Ross Paterson was instructed to request deadline extension to 30 January 2026. New solicitor must respond by this date.

Summary: Key Points to Argue Against WH

WH Claims That Are INCORRECT:

  1. "Notified in March 2021" - Misleading. The Oct 2020 leak had stopped. Al asked a question, not demanded repairs.
  2. "No response received" - FALSE. Katerina responded on 1 April 2021.
  3. "11 months of neglect" - FALSE. The 2022 leak was NEW, not continuation of 2020 issue.

Points to Strengthen Defence:

  1. Unauthorised works - Al acted without consultation
  2. Payment irregularities - Payment to JS Whitbread, not company
  3. No competitive quotes - £3,500 unverified
  4. Good faith settlement offers - £500, then £978.75 rejected
  5. Ground rent arrears - Counter-claim available

Related Pages

← Katerina-Stan Emails Katerina-Ross Emails → All Documents ← Back to Overview